2026: Downtown Square Utility Relocation Project
Downtown Square Utility Relocation Project Information
This project involves the replacement of aging underground utilities to improve the infrastructure in Covington’s downtown square. The work will include:
- Removal of old materials and installation of new sewer, water, and gas lines.
- Installation of new power and telecommunication duct bank.
- Removal and replacement of asphalt and street striping.
The Downtown Square Relocation & Replacement Project will focus on upgrading aging infrastructure within a 9-block perimeter of the square.
Red outline represents the 9-block perimeter duct bank/project area. Select map to enlarge.
KEY DATES
- October 11, 2025: Contractors will be inspecting the sewer system throughout downtown Covington. Inspections will include soft digging, but no full road closures are expected.
- February 6, 2026: Contractor’s solicitation period ends
- February 15, 2026: Guaranteed Maximum Price for construction will be presented to the city for review
- April 15, 2026: Tentative start date for construction - this date could change to before or after Apri 15th
NEWSLETTERS
PRESOLICITATION NOTICE TO SUBCONTRACTORS
Strack, Inc., acting as Construction Manager at Risk, invites qualified subcontractors to submit bids for the Downtown Square Utilities Relocation Project in Covington, GA.
Bids Due by Friday, February 6, 2026